Does the MMCD address Force Majeure events?

While the term Force Majeure is not explicitly used in MMCD documents, similar conditions are addressed in GC 13.4.1, which covers events beyond the contractor’s control. These may include natural disasters, civil unrest, and other extraordinary circumstances that prevent the fulfillment of contract obligations.