What must be included in daily Force Account reports?
Daily reports must be detailed and submitted promptly. Per Volume I, Article 4.4.6, they should include:
- Names and hours of workers involved
- Equipment used and operating hours
- Material quantities and delivery receipts
- Site conditions and activities
- Photographs (if applicable)
Reports must be signed by both the contractor and the Contract Administrator’s representative.