What must be included in daily Force Account reports?

Daily reports must be detailed and submitted promptly. Per Volume I, Article 4.4.6, they should include:

  • Names and hours of workers involved
  • Equipment used and operating hours
  • Material quantities and delivery receipts
  • Site conditions and activities
  • Photographs (if applicable)
    Reports must be signed by both the contractor and the Contract Administrator’s representative.