Which document takes priority if statements contradict across specifications, drawings, and quantities?
According to GC 2.2(1), the order of precedence is clearly defined. Generally, the Agreement and Supplementary Conditions take precedence over Specifications and Drawings. Always refer to the General Conditions for a complete breakdown.